8. Documents that define what you're actually buying
When a shipment goes wrong, the only thing that matters is what was written down before the deposit. "We agreed on WhatsApp" is not a quality standard.
### The document pack
| Document | Purpose | Non-negotiable contents |
|---|---|---|
| Specification sheet | Defines the product | Materials, tolerances, dimensions, colour references, function, packaging, marking, compliance list |
| Golden sample | Physical reference, signed and dated by both parties | Two sealed copies (one with you, one at the factory), with a photo log and a stated tolerance for colour and finish |
| Proforma invoice (PI) | Price and order summary | SKU, description, quantity, unit price, Incoterm with named place and edition, packaging, total, bank details, payment terms, lead time, price validity, HS code if agreed |
| Purchase contract | The enforceable agreement | Everything in the PI plus quality standard, inspection and remedy, delay clause, IP ownership, confidentiality, governing law and dispute resolution |
| Commercial invoice (CI) | Customs declaration | Must match the amount actually paid; consistent description, quantity, value and Incoterm with the PI and packing list |
| Packing list | Physical reconciliation | Carton count, units per carton, net/gross weight, dimensions, CBM, shipping marks |
| Transport document | Title/control depending on type | B/L (ocean) or AWB (air), shipper, consignee, notify party, description consistent with CI |
| Certificate of origin | Origin claim, preferential duty | Issued by an authorised body; non-preferential vs preferential (e.g. FTA form) as required |
| Compliance file | Market access | DoC, test reports, risk assessment, technical documentation, labels, instructions, responsible-person details |
### A proforma invoice is not a contract
Many suppliers will offer only a PI. It is a billing document: it states what you are paying for, but it usually says nothing about what happens when the goods are late, defective or non-compliant. Accept a PI as an order confirmation, and add a short purchase contract or a set of written "terms of sale" that the supplier signs and stamps. Without it, a delay clause is unenforceable and a defect claim becomes a negotiation about goodwill.
Minimum clauses to add:
- Quality: the signed golden sample is the reference; the AQL standard and defect classification in §10 apply; compliance documentation must be provided before shipment.
- Lead time: a defined number of calendar days from receipt of deposit, with the goods-ready date and a stated remedy for delay (a per-day penalty or a right to cancel). A date with no consequence is a target, not an obligation.
- Inspection and acceptance: the balance is payable only after a passed pre-shipment inspection; rework and re-inspection at the supplier's cost; a right to reject and recover the deposit for repeated failure.
- Remedy ladder: rework → sort and replace → price adjustment → reject and refund. Agree it before there is a problem.
- IP and confidentiality: see below.
- Dispute resolution: governing law, venue or arbitration institution, language, and who bears costs. Be realistic: enforcing a foreign judgment against a small Chinese entity is slow and expensive. Your real leverage is the unpaid balance and the prospect of future orders, which is why payment structure matters more than clever drafting.
### Protecting a design properly
A standard Western-style NDA is a weak instrument for contract manufacturing. Three practical issues: it is often signed by a sales entity rather than the factory; it is difficult and expensive to enforce across borders; and it does not stop the factory from making a similar product for someone else under a different name.
A more useful stack:
- An NNN agreement — non-use, non-disclosure and non-circumvention — drafted to be enforceable in the supplier's jurisdiction, in Chinese and English, signed and stamped by the actual manufacturing entity. Non-use is the important clause: it restricts using your design, tooling or specification for any purpose other than your order.
- Register rights before disclosure, in the markets where you will sell and, where commercially justified, in China: trade marks, design registrations and utility patents. A design that is public before filing is much harder to protect.
- Own the tooling explicitly: moulds, dies, plates, artwork files and test fixtures paid for by you remain your property, must be marked, cannot be used for other buyers, and must be returned or destroyed on termination. Physically mark custom moulds with your company name and photograph them.
- Split the chain for genuinely novel products: have different suppliers make different components and do final assembly elsewhere, so no single factory holds the complete design.
- Accept the limit. Once a product is publicly on sale, competitors can reverse-engineer it. Speed of brand building, channel relationships and continuous iteration protect more than paperwork.
### Invoice accuracy
The PI, CI, packing list, B/L and payment records should tell one consistent story. Asking a supplier to declare a lower value "to save duty" exposes you — the importer — to penalties, back duties, seizure and a damaged compliance record, and it corrupts the very documents you would need to make an insurance claim or a warranty claim. It is not worth it.
9. Paying without getting robbed
### Instruments compared
| Method | Buyer protection | Cost | Typical use | Watch out for |
|---|---|---|---|---|
| T/T bank wire | None once sent | Bank fee + FX spread (often 2–3% at traditional banks; lower at specialist providers) | The default for most orders | Irreversible. Verify the beneficiary, not just the email |
| Platform trade assurance / escrow | Protection against non-shipment and defined quality disputes | Platform fee, sometimes built into price | First orders, unfamiliar suppliers | Coverage is limited to the platform's criteria and timeline; it is not a substitute for inspection |
| Letter of credit (at sight) | Bank pays against conforming documents | Bank fees and document work; usually uneconomical below roughly $30,000–50,000 per order | Large orders, new counterparties | Document discrepancies are a common reason for non-payment; use an experienced bank |
| Credit card / PayPal | Chargeback rights | Higher fees (several percent) | Samples, very small orders | Many suppliers refuse them for larger orders; not practical for sea freight with no parcel tracking |
| Open account (O/A) | Maximum buyer flexibility | Supplier prices in the risk | Established relationships, large repeat buyers | Suppliers typically insure via export credit agencies and will credit-check you |
| Cash in advance, 100% | None | Low | Almost never appropriate | The single largest avoidable loss pattern for new importers |
### Structure the payment around leverage
| Structure | When it is reasonable |
|---|---|
| 30% deposit / 70% before shipment | Common standard. Acceptable only if the 70% follows a passed inspection, not before |
| 30% / 70% against bill of lading | Better cash position; the supplier holds documents until payment. Still leaves you with goods you have not inspected |
| 30% / 60% after inspection / 10% after arrival and acceptance | Negotiable with a motivated supplier; strongest practical protection |
| 100% after delivery (O/A 15–60 days) | Only after a proven track record, usually with export credit insurance behind it |
For a first order, the priority is not the smallest deposit — it is keeping the balance unpaid until an independent inspector has signed off. Once the full amount is with the factory, every quality discussion becomes a favour.
### Payment-redirection fraud (business email compromise)
The most common large loss in sourcing today is not a fake factory. It is a real supplier whose email thread has been compromised. An attacker watches an active order, then sends a plausible "our bank details have changed" message just before the deposit or balance is due, often with a lookalike domain and artificial urgency. The goods are real; the money goes somewhere else; and the factory will not release the container because it was never paid.
A non-negotiable protocol for every payment:
- Beneficiary name must exactly match the registered legal entity on the business licence and the sales contract. No personal accounts, no "our partner company", no offshore affiliate without a documented reason and a contract that names it.
- Require bank details on stamped company letterhead, with the legal name, account number, bank name and address, SWIFT/BIC, and the official company chop. Never wire based on text in an email or chat message alone.
- Treat every change of bank details as hostile until verified. Call a phone number you already had on file — from the contract, an earlier verified thread or the company website — never the number in the change request. Read the full account number, name and SWIFT back to someone you have dealt with before. Record who confirmed and when.
- Inspect the sender's address character by character and check the reply-to. Look for swapped letters, changed domains, shifted tone, unusual urgency or requests for secrecy.
- A letterhead or a bank statement is supporting evidence, not proof — both are easy to forge.
- Send a small test transfer to any new account and confirm receipt by phone before releasing the balance.
- Two-person approval: one person maintains supplier bank records, a different person authorises payment. Restrict who can edit vendor master data.
- If you have paid, act within hours: ask your bank to recall or hold the transfer, preserve the full email trail and SWIFT record, notify the genuine supplier, and report it to the relevant authority.
Also watch for the mirror image: a supplier insisting on an unprotected method, offering an unusually large discount to avoid escrow, or demanding payment within 24 hours "to hold the production slot". Legitimate factories understand that cross-border payments take time to verify.
### FX and cash
USD remains the default invoicing currency, but the supplier's costs are in CNY. For larger or repeat orders, agree an FX adjustment clause (for example, reopen pricing only if USD/CNY moves beyond an agreed band), consider holding CNY in a multi-currency account, or use a simple forward contract for orders with long lead times. Budget for both the visible wire fee and the invisible spread, and record who absorbs intermediary bank charges — short payments of $20–$50 routinely stall shipments at the worst possible moment.
10. Quality is a system, not a promise
"About 5% defects is fine" is not a quality standard. It does not say what counts as a defect, how many units will be checked, who checks, or what happens when the threshold is crossed. Without those, an inspection report is an opinion, and a dispute is unwinnable.
### AQL in one page
Commercial inspection uses statistical acceptance sampling defined by ISO 2859-1 (international), ANSI/ASQ Z1.4 (US) and GB/T 2828.1 (Chinese equivalent). The tables correspond, so naming any one of them in your purchase order puts both parties on the same page.
Three inputs determine the plan:
- Lot size — the number of units in the shipment.
- Inspection level — General Level II is the default for consumer goods. Level I reduces the sample (low-risk, trusted suppliers); Level III increases it (new factory, safety-critical, high value); special levels S-1 to S-4 suit destructive or expensive tests.
- AQL values per defect class.
Defects are classified before the inspection, in writing, with examples specific to your product:
| Class | Meaning | Usual AQL | Example |
|---|---|---|---|
| Critical | Unsafe, illegal, or a serious hazard in use | 0 — one fails the lot | Sharp exposed edge on a children's product; wrong electrical insulation |
| Major | Affects function, usability or saleability | 2.5 | Mechanism jams; dimension outside tolerance; obvious cosmetic flaw on a visible surface |
| Minor | Outside spec without affecting use | 4.0 | Tiny scuff, slight colour variance within an agreed tolerance |
For a 5,000-unit lot at General Level II, a single sampling plan draws 200 units. At AQL 2.5 for majors, the lot passes with 10 or fewer major defects and fails at 11; at AQL 4.0 for minors it passes up to 14 and fails at 15. Any critical defect fails the lot. Tighten to 1.0 or 1.5 for majors on high-value, safety-related or regulated products.
Two common misreadings: AQL 2.5 does not mean "2.5% of the order may be defective", and it does not guarantee a defect rate. It is a property of the sampling scheme's acceptance behaviour over a series of lots. Also, "AQL 2.5" alone is ambiguous — always state the standard, the inspection level, the defect classification list and the AQL for each class.
### Inspection types
| Type | When | What it catches |
|---|---|---|
| IQC / incoming material check | Before production starts | Wrong raw material or component substitution |
| DUPRO (during production) | ~20–50% complete | Process drift early enough to correct |
| PSI (pre-shipment inspection) | At least 80% produced and packed into cartons | Final verdict before the balance is paid |
| Loading supervision | Container stuffing | Wrong cartons loaded, poor stacking, unsealed container |
| Lab testing | On samples, before production | Chemical, electrical, mechanical and safety compliance — different from inspection |
Inspection and lab testing answer different questions. An inspector can confirm that 2,000 bottles match the golden sample; only a laboratory can tell you whether the coating complies with food-contact migration limits. Do not let a supplier's "we have CE" or an inspection report substitute for the relevant test report.
### Making the PSI count
- Book it backwards from the loading date, at least several days ahead, and insist the factory has ≥80% of the order packed. An inspection of a half-finished order proves nothing.
- Send the inspector the specification, the golden-sample reference, your defect classification list and the AQL values. Otherwise the inspection company applies its own defaults, which may not match what you agreed.
- Insist on random carton selection from across the lot, not from a prepared pallet.
- Require a report with dated photographs, measurements, quantities checked, defect classification against your written requirements, the AQL calculation, and a clear conform / non-conform / pending-correction conclusion. A report without photos and measurements is useless as evidence.
- Schedule it before the balance payment. This is the entire point.
### The remedy ladder
Agree in the contract, in this order:
- Conforming — ship, pay the balance.
- Non-conforming, correctable — factory sorts or reworks at its cost, then a new random sample is drawn for re-inspection. No shipment until it passes.
- Non-conforming, tolerable — a negotiated price adjustment, documented in a revised invoice, used only for defects that genuinely do not affect safety, compliance or resale.
- Fundamental failure — reject the batch, recover the deposit, and activate the dispute clause. Repeated failed re-inspections should trigger this automatically.
Agreeing the ladder before production is what turns an inspection report into leverage. Without it, a failed report just starts an argument.